Track Boss Cleveland block update 10/10/2016...
2 of 3 fixtures are finished. Fixture #1 is about %75 finished. Fixture #1 is the opperation that will hold the raw casting, so we are being careful in the design of this. It needs to be able to locate the raw casting consistently.
We are using existing OE castings to help confirm the fixture and programing.
We appreciate everybody's patience as we very slowly walk through this process. As I have stated before, it really feels like baby steps. It is nice to look back at where we have come from and what has been finished so far.
If you are interested in a Track Boss Cleveland block, please send me an email and I will put your name on our email list.
Send emails to fordmachinist@gmail.com